UEGCL · Meter Commissioning Review

Load Profile Analysis — LGZ16999346

Meter Serial: LGZ16999346 Recording Period: 2026-09-11 to 2026-10-05 Interval: 1-hour LP1 Prepared: 2026-10-12

§1Operating Summary (Normal Period)

Active Power Avg
0.05 MW
Range: 0.01 – 0.18 MW
Reactive Power
0.00–0.02 Mvar
Stable throughout
Voltage (L-N avg)
20.02 kV
Implies 34.68 kV L-L (~33 kV nominal)
Frequency
49.77–50.52 Hz
Within ±0.5 Hz tolerance
Total Energy
29 MWh
524 operating hours
Current Imbalance
0.00 %
L1=0.000 L2=0.000 L3=0.000 kA

§2Reactive Power Profile

Mvar vs Time (2026-09-11 – 2026-10-05)
DateMin MvarMax Mvar Avg MvarDay RangeAssessment
2026-09-140.000.000.000.00✓ Stable — normal variation
2026-09-150.000.010.000.01✓ Stable — normal variation
2026-09-160.000.010.000.01✓ Stable — normal variation
2026-09-170.000.010.000.01✓ Stable — normal variation
2026-09-180.000.010.000.01✓ Stable — normal variation
2026-09-190.000.000.000.00✓ Stable — normal variation
2026-09-200.000.000.000.00✓ Stable — normal variation
2026-09-210.000.010.000.01✓ Stable — normal variation
2026-09-220.000.010.000.01✓ Stable — normal variation
2026-09-230.000.010.000.01✓ Stable — normal variation
2026-09-240.000.010.000.01✓ Stable — normal variation
2026-09-250.000.010.000.01✓ Stable — normal variation
2026-09-260.000.000.000.00✓ Stable — normal variation
2026-09-270.000.000.000.00✓ Stable — normal variation
2026-09-280.000.020.010.02✓ Stable — normal variation
2026-09-290.000.010.000.01✓ Stable — normal variation
2026-09-300.000.010.000.01✓ Stable — normal variation
2026-10-010.000.010.000.01✓ Stable — normal variation
2026-10-020.000.020.000.02✓ Stable — normal variation
2026-10-030.000.010.000.01✓ Stable — normal variation
2026-10-040.000.010.000.01✓ Stable — normal variation
2026-10-050.000.010.010.01✓ Stable — normal variation

§3Key Findings

NormalReactive power is stable — daily range never exceeds 0.02 Mvar

The Mvar profile is consistent throughout the recording period with no step-changes.

WarningMeter powered on 11 recording interval(s) before first load reading

The meter recorded 11 zero-load interval(s) before the generator came online. The kWh register showed 44.74 kWh at the first loaded interval.

Confirm all CT/VT ratio parameters were finalised before the generator was synchronised, and that no parameters were changed after load came on.

CriticalEnergy delta discrepancy — kWh register does not match MW reading

The hourly kWh change differs from the instantaneous MW by more than 2% in at least one interval. Possible causes: CT/VT ratio change mid-record, clock error, or register overflow.

NormalPhase current imbalance: 0.00% — Within normal limits

L1 = 0.0000 kA, L2 = 0.0000 kA, L3 = 0.0000 kA. Within normal limits.

NormalFrequency, export energy, and status register are all nominal

Frequency 49.77–50.52 Hz (within ±0.5 Hz tolerance). Export energy stayed essentially constant throughout — no reverse-power flow events. Status register held a consistent code from first load interval onward.

§4Metering Configuration Cross-Check

ParameterMeter ReadingCross-checkStatus
System voltage (L-N) 20.02 kV avg 33 kV ÷ √3 = 19053 V ✓ Verify VT mode
Phase current (avg) L1=0.0000 L2=0.0000 L3=0.0000 kA Expected ~0.0009 kA at 0.1 MW ✓ Consistent
kWh Δ vs MW Δ kWh/h ≈ MW×1000 ±2% Verified across all 524 rows DISCREPANCY ✗
Power factor range 0.5000 – 1.0000 Expected >0.99 for large hydro Normal
Current imbalance 0.00% Limit 5%, ideal <1% OK

§5Questions to Probe the UEGCL Team

Use these to narrow down what "not reading what we expect" means before drawing conclusions.

CT / VT Configuration
What are the CT and VT nameplate ratios at this bay, and what ratios are programmed in the meter?
The meter shows 20.02 kV (L-N) and ~0.000 kA per phase avg. If the VT secondary is 190.5 V L-N and CT secondary is 5 A, the programmed ratios must match exactly. A 5% ratio error means MW and kWh are wrong by 5% across the entire record.
Expected vs Actual
Which specific parameter is different from what you expected: MW, kWh total, voltage, or Mvar?
The meter's MW (0.1 MW avg), kWh delta, and phase V/I are all internally self-consistent. Without knowing which parameter UEGCL believes is wrong, and what their reference value is, a metering error cannot be confirmed or denied.
Reference Comparison
Do you have a SCADA or EMS reading for this unit over the same period, and by how much does it differ?
The meter records 0.1 MW average for 524 hours = 29 MWh. A ratio difference points to a scale factor error; a fixed offset points to an auxiliary load or metering boundary issue.
Reactive Power Control
Who controls the AVR setpoint, and were there deliberate reactive power changes during the recording period?
The Mvar record shows a 0.02 Mvar max daily swing while MW stays constant — the signature of AVR setpoint changes or capacitor bank switching, not metering error. The control-room dispatch log will confirm.
Commissioning Sequence
Were CT/VT ratio parameters finalised before the generator was synchronised, or were any parameters changed after load came on?
If any parameter was corrected after the first load interval without resetting the accumulator, early energy may be wrongly scaled.
Metering Boundary
Is this meter on the generator terminals or the grid side of the step-up transformer, and what is the unit's rated capacity?
The voltage of 20.02 kV (L-N) implies a ~33 kV metering point. If UEGCL expects higher voltage because their reference is on the HV side of a transformer, the metering point location explains the difference. If the unit is rated above 0 MW, station auxiliary load may account for the gap.
CT Polarity
Was a CT injection test done to verify polarity and phase sequence before energisation?
Export energy has stayed essentially constant — no reverse-power flow detected. A reversed CT polarity would flip Q sign on one phase. The observed Mvar step-changes look like deliberate setpoint changes rather than polarity issues, but this check eliminates the possibility entirely.
Old Meter Baseline
What was the old meter's final kWh reading at changeover?
The new meter started at 44.74 kWh. Without the old meter's closing reading, the absolute kWh total cannot be validated. The internal delta-vs-MW check confirms the meter is accumulating correctly from its own reference point.

§6Recommended Next Steps

Action 1Verify VT ratio programming and voltage reporting mode (L-N vs L-L)

Compare the VT nameplate ratio against the programmed value in OBIS 1-4:32.5.0. Confirm L-N or L-L convention. This single check resolves the most common "wrong voltage" complaint.

Action 2Obtain SCADA kWh/MW for the same period and compute the ratio

A ratio error points to a CT or VT scale factor problem. An offset points to metering boundary or auxiliary load. A ratio within ±1% confirms the meter is correctly scaled.

Action 3Get the AVR setpoint log from the control room for the recording period

Confirms whether Mvar step-changes are deliberate (normal) or unintended. Either outcome closes the reactive power finding.