UEGCL · Meter Commissioning Review
| Date | Min Mvar | Max Mvar | Avg Mvar | Day Range | Assessment |
|---|---|---|---|---|---|
| 2026-09-15 | 0.03 | 0.07 | 0.04 | 0.04 | ✓ Stable — normal variation |
| 2026-09-16 | 0.03 | 0.06 | 0.04 | 0.03 | ✓ Stable — normal variation |
| 2026-09-17 | 0.02 | 0.07 | 0.05 | 0.05 | ✓ Stable — normal variation |
| 2026-09-18 | 0.02 | 0.05 | 0.04 | 0.03 | ✓ Stable — normal variation |
| 2026-09-19 | 0.02 | 0.05 | 0.04 | 0.03 | ✓ Stable — normal variation |
| 2026-09-20 | 0.01 | 0.06 | 0.04 | 0.05 | ✓ Stable — normal variation |
| 2026-09-21 | 0.01 | 0.02 | 0.01 | 0.01 | ✓ Stable — normal variation |
| 2026-09-22 | 0.01 | 0.04 | 0.02 | 0.03 | ✓ Stable — normal variation |
| 2026-09-23 | 0.01 | 0.02 | 0.02 | 0.01 | ✓ Stable — normal variation |
| 2026-09-24 | 0.01 | 0.03 | 0.02 | 0.02 | ✓ Stable — normal variation |
| 2026-09-25 | 0.00 | 0.02 | 0.02 | 0.02 | ✓ Stable — normal variation |
| 2026-09-26 | 0.01 | 0.06 | 0.04 | 0.05 | ✓ Stable — normal variation |
| 2026-09-27 | 0.04 | 0.07 | 0.05 | 0.03 | ✓ Stable — normal variation |
| 2026-09-28 | 0.04 | 0.05 | 0.05 | 0.01 | ✓ Stable — normal variation |
| 2026-09-29 | 0.04 | 0.06 | 0.05 | 0.02 | ✓ Stable — normal variation |
| 2026-09-30 | 0.04 | 0.07 | 0.05 | 0.03 | ✓ Stable — normal variation |
| 2026-10-01 | 0.04 | 0.06 | 0.05 | 0.02 | ✓ Stable — normal variation |
| 2026-10-02 | 0.04 | 0.07 | 0.05 | 0.03 | ✓ Stable — normal variation |
| 2026-10-03 | 0.04 | 0.05 | 0.05 | 0.01 | ✓ Stable — normal variation |
| 2026-10-04 | 0.04 | 0.05 | 0.05 | 0.01 | ✓ Stable — normal variation |
| 2026-10-05 | 0.04 | 0.12 | 0.05 | 0.08 | ✓ Stable — normal variation |
Before load (pre-load rows) phase voltages read 215.4 kV. Once load came on they settled to 251.4 kV. These are not compatible as the same mode: 215.4 kV is the line-to-line voltage of a 220 kV bus; 251.4 kV is the line-to-neutral voltage (220000 ÷ √3 = 127017 V). A VT ratio or reporting-mode change occurred during the commissioning window.
If UEGCL's reference system expects 220 kV (L-L) and the meter is reporting 251.4 kV (L-N), this single configuration difference explains the "wrong voltage" complaint without any physical re-wiring.
The Mvar profile is consistent throughout the recording period with no step-changes.
The meter recorded 17 zero-load interval(s) before the generator came online. The kWh register showed 51.16 kWh at the first loaded interval.
Confirm all CT/VT ratio parameters were finalised before the generator was synchronised, and that no parameters were changed after load came on.
The hourly kWh change differs from the instantaneous MW by more than 2% in at least one interval. Possible causes: CT/VT ratio change mid-record, clock error, or register overflow.
L1 = 0.1103 kA, L2 = 0.1007 kA, L3 = 0.1025 kA. Exceeds the 5% limit.
Frequency 49.77–50.52 Hz (within ±0.5 Hz tolerance). Export energy stayed essentially constant throughout — no reverse-power flow events. Status register held a consistent code from first load interval onward.
| Parameter | Meter Reading | Cross-check | Status |
|---|---|---|---|
| System voltage (L-L) | 251.98 kV avg | 220 kV ÷ √3 = 127017 V (L-L) | Verify VT mode |
| Phase current (avg) | L1=0.1103 L2=0.1007 L3=0.1025 kA | Expected ~0.0001 kA at 0.1 MW ✓ | Consistent |
| kWh Δ vs MW | Δ kWh/h ≈ MW×1000 ±2% | Verified across all 489 rows | DISCREPANCY ✗ |
| Power factor range | 0.6250 – 1.0000 | Expected >0.99 for large hydro | Normal |
| Current imbalance | 9.16% | Limit 5%, ideal <1% | HIGH |
Use these to narrow down what "not reading what we expect" means before drawing conclusions.
Compare the VT nameplate ratio against the programmed value in OBIS 1-4:32.5.0. Confirm L-N or L-L convention. This single check resolves the most common "wrong voltage" complaint.
A ratio error points to a CT or VT scale factor problem. An offset points to metering boundary or auxiliary load. A ratio within ±1% confirms the meter is correctly scaled.
Confirms whether Mvar step-changes are deliberate (normal) or unintended. Either outcome closes the reactive power finding.