UEGCL · Meter Commissioning Review
| Date | Min Mvar | Max Mvar | Avg Mvar | Day Range | Assessment |
|---|---|---|---|---|---|
| 2026-10-01 | 0.75 | 2.80 | 1.51 | 2.05 | ⚠ Step-changes present — likely AVR or compensation switching |
| 2026-10-02 | 0.59 | 3.47 | 1.69 | 2.88 | ⚠ Step-changes present — likely AVR or compensation switching |
| 2026-10-03 | 0.26 | 4.38 | 2.12 | 4.12 | ⚠ Very large swing — multiple step-changes detected |
| 2026-10-04 | 0.36 | 1.95 | 0.94 | 1.59 | Moderate variation |
| 2026-10-05 | 0.61 | 4.53 | 2.68 | 3.92 | ⚠ Very large swing — multiple step-changes detected |
Active power holds steady at ~8.8 MW throughout. Reactive power jumps between discrete levels in sharp step-changes that hold for several hours. Worst day: 2026-10-03 with 4.12 Mvar range (min 0.26, max 4.38 Mvar). MW does not move when Mvar jumps — this rules out load changes.
This is the behaviour of AVR setpoint adjustments or capacitor bank switching. 0 day(s) are rock-stable (<0.5 Mvar range), confirming the meter holds steady Q readings when the system is stable.
The meter recorded 3 zero-load interval(s) before the generator came online. The kWh register showed 7,550.41 kWh at the first loaded interval.
Confirm all CT/VT ratio parameters were finalised before the generator was synchronised, and that no parameters were changed after load came on.
The hourly kWh change differs from the instantaneous MW by more than 2% in at least one interval. Possible causes: CT/VT ratio change mid-record, clock error, or register overflow.
L1 = 0.4363 kA, L2 = 0.0000 kA, L3 = 0.4571 kA. Exceeds the 5% limit.
Coherent across V, I, P — not a metering artefact. Confirm with control-room log.
Frequency 49.84–50.51 Hz (within ±0.5 Hz tolerance). Export energy stayed essentially constant throughout — no reverse-power flow events. Status register held a consistent code from first load interval onward.
| Parameter | Meter Reading | Cross-check | Status |
|---|---|---|---|
| System voltage (L-N) | 7.69 kV avg | 13 kV ÷ √3 = 7506 V ✓ | Verify VT mode |
| Phase current (avg) | L1=0.4363 L2=0.0000 L3=0.4571 kA | Expected ~0.3792 kA at 8.8 MW ✓ | Consistent |
| kWh Δ vs MW | Δ kWh/h ≈ MW×1000 ±2% | Verified across all 99 rows | DISCREPANCY ✗ |
| Power factor range | 0.8405 – 1.0000 | Expected >0.99 for large hydro | Normal |
| Current imbalance | 153.49% | Limit 5%, ideal <1% | HIGH |
Use these to narrow down what "not reading what we expect" means before drawing conclusions.
Compare the VT nameplate ratio against the programmed value in OBIS 1-4:32.5.0. Confirm L-N or L-L convention. This single check resolves the most common "wrong voltage" complaint.
A ratio error points to a CT or VT scale factor problem. An offset points to metering boundary or auxiliary load. A ratio within ±1% confirms the meter is correctly scaled.
Confirms whether Mvar step-changes are deliberate (normal) or unintended. Either outcome closes the reactive power finding.