UEGCL · Meter Commissioning Review
| Date | Min Mvar | Max Mvar | Avg Mvar | Day Range | Assessment |
|---|---|---|---|---|---|
| 2000-01-01 | 4.42 | 8.81 | 6.71 | 4.39 | ⚠ Very large swing — multiple step-changes detected |
| 2000-01-02 | 0.50 | 7.12 | 2.05 | 6.62 | ⚠ Very large swing — multiple step-changes detected |
| 2000-01-03 | 0.37 | 4.21 | 2.00 | 3.84 | ⚠ Very large swing — multiple step-changes detected |
| 2026-09-25 | 3.34 | 3.34 | 3.34 | 0.00 | ✓ Stable — normal variation |
Before load (pre-load rows) phase voltages read 34.6 kV. Once load came on they settled to 19.5 kV. These are not compatible as the same mode: 34.6 kV is the line-to-line voltage of a 33 kV bus; 19.5 kV is the line-to-neutral voltage (33000 ÷ √3 = 19053 V). A VT ratio or reporting-mode change occurred during the commissioning window.
If UEGCL's reference system expects 33 kV (L-L) and the meter is reporting 19.5 kV (L-N), this single configuration difference explains the "wrong voltage" complaint without any physical re-wiring.
Active power holds steady at ~11.6 MW throughout. Reactive power jumps between discrete levels in sharp step-changes that hold for several hours. Worst day: 2000-01-02 with 6.62 Mvar range (min 0.50, max 7.12 Mvar). MW does not move when Mvar jumps — this rules out load changes.
This is the behaviour of AVR setpoint adjustments or capacitor bank switching. 1 day(s) are rock-stable (<0.5 Mvar range), confirming the meter holds steady Q readings when the system is stable.
The meter recorded 2 zero-load interval(s) before the generator came online. The kWh register showed 11,724.50 kWh at the first loaded interval.
Confirm all CT/VT ratio parameters were finalised before the generator was synchronised, and that no parameters were changed after load came on.
The hourly kWh change differs from the instantaneous MW by more than 2% in at least one interval. Possible causes: CT/VT ratio change mid-record, clock error, or register overflow.
L1 = 0.2062 kA, L2 = 0.2112 kA, L3 = 0.2085 kA. Below 5% limit but above 1% ideal — monitor.
Frequency 49.81–50.37 Hz (within ±0.5 Hz tolerance). Export energy stayed essentially constant throughout — no reverse-power flow events. Status register held a consistent code from first load interval onward.
| Parameter | Meter Reading | Cross-check | Status |
|---|---|---|---|
| System voltage (L-N) | 19.53 kV avg | 33 kV ÷ √3 = 19053 V ✓ | Verify VT mode |
| Phase current (avg) | L1=0.2062 L2=0.2112 L3=0.2085 kA | Expected ~0.1986 kA at 11.6 MW ✓ | Consistent |
| kWh Δ vs MW | Δ kWh/h ≈ MW×1000 ±2% | Verified across all 74 rows | DISCREPANCY ✗ |
| Power factor range | 0.7720 – 0.9992 | Expected >0.99 for large hydro | Normal |
| Current imbalance | 2.40% | Limit 5%, ideal <1% | Borderline |
Use these to narrow down what "not reading what we expect" means before drawing conclusions.
Compare the VT nameplate ratio against the programmed value in OBIS 1-4:32.5.0. Confirm L-N or L-L convention. This single check resolves the most common "wrong voltage" complaint.
A ratio error points to a CT or VT scale factor problem. An offset points to metering boundary or auxiliary load. A ratio within ±1% confirms the meter is correctly scaled.
Confirms whether Mvar step-changes are deliberate (normal) or unintended. Either outcome closes the reactive power finding.