UEGCL · Meter Commissioning Review
| Date | Min Mvar | Max Mvar | Avg Mvar | Day Range | Assessment |
|---|---|---|---|---|---|
| 2026-09-17 | 2.01 | 3.80 | 2.33 | 1.79 | Moderate variation |
| 2026-09-18 | 0.98 | 5.08 | 3.04 | 4.10 | ⚠ Very large swing — multiple step-changes detected |
| 2026-09-19 | 0.99 | 5.05 | 2.60 | 4.06 | ⚠ Very large swing — multiple step-changes detected |
| 2026-09-20 | 3.02 | 5.07 | 3.73 | 2.05 | ⚠ Step-changes present — likely AVR or compensation switching |
| 2026-09-21 | 3.01 | 3.07 | 3.03 | 0.06 | ✓ Stable — normal variation |
| 2026-09-22 | 1.01 | 4.09 | 2.89 | 3.08 | ⚠ Step-changes present — likely AVR or compensation switching |
| 2026-09-23 | 4.01 | 4.09 | 4.05 | 0.08 | ✓ Stable — normal variation |
| 2026-09-24 | 4.02 | 4.09 | 4.05 | 0.07 | ✓ Stable — normal variation |
Before load (pre-load rows) phase voltages read 11.4 kV. Once load came on they settled to 6.3 kV. These are not compatible as the same mode: 11.4 kV is the line-to-line voltage of a 11 kV bus; 6.3 kV is the line-to-neutral voltage (11000 ÷ √3 = 6351 V). A VT ratio or reporting-mode change occurred during the commissioning window.
If UEGCL's reference system expects 11 kV (L-L) and the meter is reporting 6.3 kV (L-N), this single configuration difference explains the "wrong voltage" complaint without any physical re-wiring.
Active power holds steady at ~38.5 MW throughout. Reactive power jumps between discrete levels in sharp step-changes that hold for several hours. Worst day: 2026-09-18 with 4.10 Mvar range (min 0.98, max 5.08 Mvar). MW does not move when Mvar jumps — this rules out load changes.
This is the behaviour of AVR setpoint adjustments or capacitor bank switching. 3 day(s) are rock-stable (<0.5 Mvar range), confirming the meter holds steady Q readings when the system is stable.
The meter recorded 4 zero-load interval(s) before the generator came online. The kWh register showed 32,094.68 kWh at the first loaded interval.
Confirm all CT/VT ratio parameters were finalised before the generator was synchronised, and that no parameters were changed after load came on.
The hourly kWh delta matches the instantaneous MW reading to within ±2% across all 167 operating intervals. The billing quantity is not in question.
L1 = 1.9940 kA, L2 = 2.0088 kA, L3 = 2.0381 kA. Below 5% limit but above 1% ideal — monitor.
Coherent across V, I, P — not a metering artefact. Confirm with control-room log.
Frequency 49.78–50.35 Hz (within ±0.5 Hz tolerance). Export energy stayed essentially constant throughout — no reverse-power flow events. Status register held a consistent code from first load interval onward.
| Parameter | Meter Reading | Cross-check | Status |
|---|---|---|---|
| System voltage (L-N) | 6.34 kV avg | 11 kV ÷ √3 = 6351 V ✓ | Verify VT mode |
| Phase current (avg) | L1=1.9940 L2=2.0088 L3=2.0381 kA | Expected ~2.0254 kA at 38.5 MW ✓ | Consistent |
| kWh Δ vs MW | Δ kWh/h ≈ MW×1000 ±2% | Verified across all 167 rows | Verified ✓ |
| Power factor range | 0.9912 – 0.9997 | Expected >0.99 for large hydro | Normal |
| Current imbalance | 2.19% | Limit 5%, ideal <1% | Borderline |
Use these to narrow down what "not reading what we expect" means before drawing conclusions.
Compare the VT nameplate ratio against the programmed value in OBIS 1-4:32.5.0. Confirm L-N or L-L convention. This single check resolves the most common "wrong voltage" complaint.
A ratio error points to a CT or VT scale factor problem. An offset points to metering boundary or auxiliary load. A ratio within ±1% confirms the meter is correctly scaled.
Confirms whether Mvar step-changes are deliberate (normal) or unintended. Either outcome closes the reactive power finding.